Metric Distance Ranking Technique for Fuzzy Critical Path Analysis
OLADEINDE, M.H. & OLADEINDE, C.A.
Abstract
In this paper, fuzzy critical path analysis of a project network is carried out.
Metric distance ranking technique is used to order fuzzy numbers during the forward and
backward pass computations to obtain the earliest start, earliest finish, latest start and latest
finish times of the project’s activities. A numerical example is presented with a detailed step
by step solution. The results of the numerical example presented are in agreement with
published results in literature using other fuzzy ranking technique.
Keywords
fuzzy; metric distance; critical path method; total float
|
|